Travelodge Bromley

Client

Henry Boot Developments

Value

£4.5M

Sector

Commercial/Office Fit-Out

Timeline

1 Year

Location

Bromley

Project Summary

H&J Martin Construction completed a £4.5m Travelodge Hotel for their Client, Henry Boot Developments. The yearlong project involved alterations to an existing 3 storey building including change of use to part of ground floor 2 upper floors from retail and offices. A new steel framed fourth storey was installed to create a 59-bedroom Travelodge Hotel over the 3 floors with 4 retail units to the ground floor.

Project Gallery

Project Details

The site was very restricted with a pedestrian shopping mall as a boundary on 2 sides, with a shared service yard on the 3rd side and public footpath on the 4th side. Two of the retails units on the ground floor remained live during the works. All works and deliveries had to be carefully co-ordinated ensuring no effect on the other businesses.

Works involved the demolition of the existing entrance and stairwell to create of a new four storey steel framed front extension incorporating a new hotel entrance foyer, stair case and new 2nd lift as well as replacement of the existing external fire escape. The façade was clad in a mixture of Marley cladding panels and brick slip with a single ply membrane roof to the main building and a green roof to the stair core along with new windows and curtain walling throughout.

Internally everything was stripped back to the concrete frame with new M&E services, lifts, partitions, ceilings, joinery, wall & floor finishes as well as fitted furniture, fixtures and fittings. Bathrooms to the 1st floor were constructed traditionally with prefinished bathrooms PODS being used on the 2nd & 3rd floor which were craned into position.

Have a Project in Mind or Just Want to Know More?

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

H&J Martin Group

Senior Leadership Hierarchy

Group Directors
Kirk Jamison – Group Commercial Director
Kieron Millar – Group Managing Director
Jim Gray – Group Operations Director

Divisional / Regional Leadership
Chris Reid – Facilities Management Director
Stephen Byrne – Regional Director (ROI)
Peter Hamlin – Fit-Out Commercial Director
Kevin Sage – Fit-Out Director
Rosewood Director – Rosewood Bespoke Joinery

Group Support Functions
Human Resources – Peter Carson, Hannah McCann, Aimee Patterson, Jamie Ingram
Health & Safety – Ian Johnston, Geraldine McCambridge, Helena Smith
Marketing – Kerry Reid

Elmwood Protection Services

Senior Leadership Hierarchy

Leadership
Kieron Millar – Managing Director (H&J Martin Group / Elmwood Protection Services)

Senior Management
Tony Watson – Head of Operations
John McConnell – Head of Strategy

Operational Management
Richard Duncan – D&G Manager
Connor Laverty – F&S Manager

Group Support (H&J Martin Group)
Human Resources – Peter Carson, Hannah McCann, Aimee Patterson, Jamie Ingram
Health & Safety – Ian Johnston, Geraldine McCambridge, Helena Smith
Marketing – Kerry Reid

Rosewood Bespoke Joinery

Senior Leadership Hierarchy

Leadership
Kirk Jamison – Managing Director
James Rushe – General Manager

Contract & Commercial
Glen Horan – Contract Manager
Brian Millar – Estimator

Group Support
Human Resources – Peter Carson, Hannah McCann, Aimee Patterson, Jamie Ingram
Health & Safety – Ian Johnston, Geraldine McCambridge, Helena Smith
Marketing – Kerry Reid